Case Study: Pier Pavilion at Barangaroo
A complex CLT roof structure in a busy location presented NeXTimber with an interesting set of challenges to tackle.
Image credit: Rory Gardiner.
H3 Treated NeXTimber Cross Laminated Timber (CLT)
Besley & Spresser
THE BRIEF
NeXTimber was engaged to support Stephen Edwards Construction (SEC) with the supply of CLT for the unique project located on Barangaroo Harbour.

Image credit: Rory Gardiner

THE PROCESS
NeXTimber supported SEC, the consultant team and the installers to develop a detailed and coordinated BIM of the structure.
This required several design iterations balancing design, manufacturing and installation; factoring cost and time.
NeXTimber converted the design model, manufactured the complex panels and managed the challenging logistics into the heart of Sydney CBD for a successful delivery and installation.

CHALLENGES & SOLUTIONS
With this project being a Design & Construct (D&C) contract, the design still required significant design resolution before it was suitable to commence production.
Design coordination between parties (builder, engineers, installers, NeXTimber® and the steel fabricator) was critical to resolve interfaces given the intricate geometry and complex connections between steel structure and CLT, further challenged by the critical timeline and fabrication of the steel structure dictated.
The design team opted for using NeXTimber® CLT manufactured using H3 treated feedstock and pre-fitted temporary construction membrane.
The complex geometry of the CLT panels involved intricate CNC processing, and the delicate panel shapes required novel temporary strengthening and careful handling for safe transport and installation.
The irregular and oversized (up to 3.5m wide) panels required a careful transportation plan, and delivery times were limited given the central Sydney CBD site.
INSTALLATION
The delicate, irregular shaped panels required temp bracing through lifting and the complex geometry and connection detailing required accurate manufacturing and sequence planning. In addition, pre-installed CLT packers were required in some locations to allow for connection to the steel sub structure.