Case Study: Tonsley Technical College
Responding to a request to investigate different options for a mass timber structure, NeXTimber worked alongside project stakeholders to provide a CLT solution for this specialist education institution in South Australia.
Image credit: Sarah Constructions
NeXTimber brings engineered timber to the heart of innovation
At the Tonsley Innovation District in Adelaide, the Factory of the Future education centre is setting the stage for how Australia will train the workforce of tomorrow. It brings together Flinders University, Tonsley Technical College and industry partners to deliver hands-on training in construction, advanced manufacturing, engineering and energy. From the earliest stages, Timberlink’s NeXTimber team was engaged to support the project’s goal of using locally made CLT.

FROM CONCEPT TO CONSTRUCTION
In late 2022, project architect Das Studio approached us to explore how CLT could help meet their sustainability and prefabrication goals. Over the course of the next 18 months, our team worked collaboratively with Das Studio and engineers from Innovis to provide technical support, consultation on manufacturing and buildability of CLT elements as well as costing advice for the client through the design iterations.
When Sarah Constructions joined as the main contractor, the NeXTimber team played a key supporting role to their project delivery team to assist with the detailed mass timber solution alongside other timber and specialist subcontractors such as Standstruct.
PRECISION MEETS PERFORMANCE
For this project, NeXTimber was selected as the supplier of CLT for floor and roof elements. We manufactured and delivered nearly 200 CLT panels for floor and roof elements – some as large as 37 square metres and weighing up to 5 tonnes. All panels were produced at our Tarpeena facility using radiata pine from responsibly managed plantations in the Green Triangle, the forestry region spanning southeast South Australia and southwest Victoria.
We produced manufacturing and logistics documentation, based on the technical design provided by the engineering and architectural teams. This included 3D manufacturing models, shop drawings, and coordination with supply partners to manage delivery and installation sequencing. In total, we delivered 22 truckloads of precision-cut panels, each arriving on site in the exact order required by the customer for efficient installation.


NAVIGATING COMPLEXITY
Large panel sizes, tight timelines and the high-profile nature of the site made planning and coordination critical. We developed a tailored logistics solution with our transport partners to get multiple oversized trucks to site daily, safely and on time.
A BLUEPRINT FOR WHAT'S NEXT
This project showed what’s possible when design ambition meets technical know-how. By working together across architecture, engineering and construction, we delivered more than just timber – we helped bring a bold educational vision to life. The result is a landmark facility built with Australian grown and manufactured CLT and designed to inspire future makers, builders and innovators.